GREEN LINE UNDERGROUND AND ELEVATED METRO – (MD’s Exp.)

GREEN LINE UNDERGROUND AND ELEVATED METRO – (MD’s Exp.)

The project comprises two 16 km twin bore rail tunnel; 6 under ground stations including one interchange station; 2 switch boxes; 6 evacuation shafts, 1 trough and 3 energy transfer stations.

Scope of Work:

  • LOD 350/400 (BIM Modelling for MEP)
  • LOD 500 (BIM Modelling for Architectural, Structural & MEP)
  • BIM Laser Scanning Services for As-Built
  • As-Built 3D/2D Documentation for Five Stations

BIM Specialist Services

  • The client BIM requirements & Scope Matrix were clear and the COBIe requirements were of HIGH level.
  • Clarity in requirements  and  inputs  resulted  in  qualitative  and  time aspects and helped to enhance better quality deliverables and speedy delivery.
  • Pioneer in the Laser Scanning process and methodology.